Roads · Cot House, by Dunoon
Cot House Bridge repairs move to spring 2027
Published 2 November 2026
Source: Argyll and Bute Council
Community & Local · Economy & Finance · Politics & Government
The council and its contractor have postponed a £600,000 repair so the waterproofing is not done in winter. The price, the council says, does not change.
What is known
- Argyll and Bute Council’s release is dated 2 November 2026. Planned repairs will now begin in spring 2027.
- The council says delays in contract mobilisation and scaffolding would have pushed waterproofing into winter, and that weather, road salt, high water and short daylight make that unsuitable.
- The contract price will not be affected. The council describes the work as a £600,000 investment to extend the life of the bridge.
- Work will be one lane at a time. The road surface comes off, the concrete deck is inspected and repaired, then waterproofed and resurfaced before the other lane is done. Soffit and elevation defects are to be repaired at the same time.
- The bridge has specialist half-joint detailing. The full extent of repairs will be confirmed only once the deck is exposed.
- Councillor John Armour, policy lead for roads, called the delay regrettable and referred to Storm Boelo as a reason not to work deeper into winter.
What is not known
- The release gives a season, spring 2027, not a start date.
- The council’s news page gives the date 2 November and does not give an exact time. We have placed it in this edition because that date is the opening day. We cannot prove it was published after 5am.
- We do not know the full repair list. The council says that list waits on the inspection.
We will report more when we have the facts.
Editor’s Comment
“The £600,000 set aside to look after Cot House Bridge is still in place, and the work has moved to spring, when the weather should be better for it. When the start date is published, we’ll share it here so everyone can plan ahead.”
-Ed.
Fact check
Confirmed by the council
Everything dated and priced above is from the council’s own release. The spring start, and the final list of repairs, are not yet facts.
Sources, and where they stand
- What it is
- Local authority
- Funding
- Public. Council tax, Scottish Government grant and other public income.
- Leaning
- Not a newspaper. The release is the council’s own account. Councillors belong to parties; the text is an institutional notice, not a party paper.
Checked 9 November 2026
A leaning note says who is speaking, and who pays them. It is not a verdict on a single sentence. We do not invent a left–right score when we do not have a careful one.
Report an error